What is the average annualised Power Usage Effectiveness (PUE) of data centres used to house those servers employed in processing Ordnance Survey’s data?
Thank you for your e-mail dated 29th September 2011. I can confirm that Ordnance Survey does hold this information.
We have two Data Centres, the first is currently running at 63kW IT load and the second is 274kW IT load.
As the requested information has been provided, we have determined that in all the circumstances of this case the Public interest test is not applicable.
If you are unhappy with our response, you may raise an appeal to our Appeals Officer at:
EIR Appeals Officer
Ordnance Survey
Adanac Drive
SOUTHAMPTON
SO16 0AS
Please include the reference number below. The Appeals Officer will ensure that the process has been followed correctly, questioning any decisions taken regarding the original response and recommending disclosure of additional information if appropriate.
Thank you for your enquiry.
Reference number: EIR11224/September 2011